Trouble: The Marines Won't Get Their CH-53K LOC Helicopter Until 2021 Due to Multiple Design Deficiencies

https://www.dvidshub.net/image/4394438/first-ch-53k-king-stallion-arrives-mcas-new-river

Trouble: The Marines Won't Get Their CH-53K LOC Helicopter Until 2021 Due to Multiple Design Deficiencies

How could this happen?

Flight testing is ongoing with four engineering and manufacturing development (EMD) aircraft, three system development test articles and a ground test vehicle.

The initial operational capability (IOC) date of the CH-53K won’t occur this December, a report from the office of Director, Operational Test and Evaluation (DOT&E) suggests.

Early testing has uncovered multiple design deficiencies that are needed to be corrected. Testers have discovered “airspeed indication anomalies, low reliability of the main rotor gearbox, hot gas impingement on aircraft structures, tail boom and tail rotor structural problems, overheating of main rotor dampers.”

As a result, IOT&E has been pushed back to early 2021.

As reported by Rotor & Wing International, the first of about 200 CH-53Ks the Marine Corps is buying from Sikorsky under a $25 billion contract was delivered in May to Air Station New River in North Carolina, where it will undergo further testing in preparation for IOC in 2019. A second aircraft is scheduled for delivery in early 2019, and at least 22 others are in some stage of production, according to Sikorsky.

Because there is a lag between program evaluations and publication of the DOT&E report, Sikorsky CH-53K Program Director Bill Falk said many items the company anticipated in the report are already resolved.

“We remain aligned on a program plan with [Naval Air Systems Command] and the USMC to support the first CH-53K deployment in 2023-2024,” Falk, said Jan. 31 in an emailed statement. “Resolution of technical issues are in process with majority already resolved.”

“Of those design items not yet closed, we have an agreed joint integrated path forward to have solutions in place to support IOT&E and first CH-53K deployment in 2023-2024,” he added.

Flight testing is ongoing with four engineering and manufacturing development (EMD) aircraft, three system development test articles and a ground test vehicle. Those seven flyable aircraft have flown a total 1,212 hours as of September, according to the report.

Live fire testing has shown the King Stallion is more resistant to small-arms and automatic weapons and man-portable air-defense systems than is the CH-53E it will replace.

“The CH-53K is currently on track to meet the survivability KPP but not without mitigations to address deficiencies uncovered in testing,” the report says. “This includes a self-sealing coating for the main gearbox lubrication sump, which the Navy is currently investigating. Any design changes to the aircraft design to address technical deficiencies may require additional live fire testing to fully assess their effects on aircraft survivability. The planned Phase II live fire testing against objective threats … has not been funded. This phase is essential for an adequate survivability assessment against operationally relevant threats.”

Actually the CH-53K King Stallion provides three times the heavy-lift capability of its predecessor, the CH-53E. This increased payload capability can take the form of a variety of relevant payloads ranging from an internally loaded High Mobility Multipurpose Wheeled Vehicle (HMMWV) or the European Fennek armored personnel carrier, and up to three independent external loads at once, which gives incredible mission flexibility and system efficiency.

This article by Dario Leone originally appeared on The Aviation Geek Club in 2019.